26INR0269 · Solar · Stonewall County
Moccasin Solar
Moccasin Solar is a 604 MW solar project in Stonewall County, Texas, connecting at Tapping the 345 kV Line from Kirchhoff (Bus# 60707) to Clear Crossing (Bus# 60515). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/06/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0269
- Capacity
- 604 MW
- Fuel
- Solar (PV)
- County
- Stonewall County
- Interconnecting entity
- Swenson Solar LLC
- Projected COD
- 07/06/2027
- Entered queue
- 09/01/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/08/2026FIS Requested → FIS Approved
- 09/04/2024FIS Approved → IA Signed
- 09/01/2023Entered the queue with 604 MW, projected COD 07/06/2027
- 09/01/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.