LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0269 · Solar · Stonewall County

Moccasin Solar

Moccasin Solar is a 604 MW solar project in Stonewall County, Texas, connecting at Tapping the 345 kV Line from Kirchhoff (Bus# 60707) to Clear Crossing (Bus# 60515). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/06/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0269
Capacity
604 MW
Fuel
Solar (PV)
Interconnecting entity
Swenson Solar LLC
Projected COD
07/06/2027
Entered queue
09/01/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/08/2026
    FIS Requested → FIS Approved
  • 09/04/2024
    FIS Approved → IA Signed
  • 09/01/2023
    Entered the queue with 604 MW, projected COD 07/06/2027
  • 09/01/2023
    Screening → FIS Requested

Other projects at this substation