26INR0253 · Solar · Van Zandt County
Goldfinch Solar
Goldfinch Solar is a 151 MW solar project in Van Zandt County, Texas, connecting at Tap Connection Bus 2485 Poetry Switch to 3103 Shamburger Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0253
- Capacity
- 151 MW
- Fuel
- Solar (PV)
- County
- Van Zandt County
- Interconnecting entity
- BT DJ4M Solar, LLC
- Projected COD
- 03/31/2029
- Entered queue
- 09/15/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/15/2023Entered the queue with 151 MW, projected COD 03/31/2029
- 09/15/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.