LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0184 · BESS · Lamar County

Arc Energy Storage

Arc Energy Storage is a 204 MW battery storage project in Lamar County, Texas, connecting at Tap 138kV 1693 Paris Switch - 11806 ENLOE T8. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0184
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
Paris Energy Storage, LLC
Projected COD
06/30/2028
Entered queue
07/25/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/02/2025
    FIS Requested → FIS Approved
  • 07/25/2023
    Entered the queue with 204 MW, projected COD 06/30/2028
  • 07/25/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.