Solar Star Frontier BESS

Solar Star Frontier BESS is a 101 MW battery storage project in Cameron County, Texas, connecting at 8656 Luna 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/27/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0181
Capacity
101 MW
Fuel
BESS (BA)
Substation
8656 Luna 138kV
Interconnecting entity
Solar Star Frontier BESS, LLC
Projected COD
02/27/2029
Entered queue
06/28/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/18/2023
    Screening → FIS Requested
  • 06/28/2023
    Entered the queue with 101 MW, projected COD 02/27/2029

Other projects at this substation