LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0162 · BESS · Nacogdoches County

Timberline Storage

Timberline Storage is a 100 MW battery storage project in Nacogdoches County, Texas, connecting at Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/05/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0162
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
Timberline Renewables, LLC
Projected COD
10/05/2029
Entered queue
08/04/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/04/2023
    Entered the queue with 100 MW, projected COD 10/05/2029
  • 08/04/2023
    Screening → FIS Requested

Other projects at this substation

Timberline SolarSolar201 MWFIS Requested