Pioneer Hutt Solar (Alternative POI)
Pioneer Hutt Solar (Alternative POI) is a 116 MW solar project in Midland County, Texas, connecting at TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0121
- Capacity
- 116 MW
- Fuel
- Solar (PV)
- County
- Midland County
- Interconnecting entity
- NextEra Energy Interconnection Holdings LLC
- Projected COD
- 07/01/2028
- Entered queue
- 06/12/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/12/2023Entered the queue with 116 MW, projected COD 07/01/2028
- 06/12/2023Screening → FIS Requested