26INR0098 · Solar · Freestone County
Douie Solar
Douie Solar is a 221 MW solar project in Freestone County, Texas, connecting at Tap 138 kV 3501 Sea way Teague - 3394 Jewett. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0098
- Capacity
- 221 MW
- Fuel
- Solar (PV)
- County
- Freestone County
- Interconnecting entity
- Buffalo Spring Solar LLC
- Projected COD
- 04/18/2028
- Entered queue
- 05/12/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/08/2026FIS Approved → IA Signed
- 07/07/2025FIS Requested → FIS Approved
- 05/12/2023Entered the queue with 221 MW, projected COD 04/18/2028
- 05/12/2023Screening → FIS Requested