25INR0853 · BESS · Tom Green County
Tango Lily BESS
Tango Lily BESS is a 201 MW battery storage project in Tom Green County, Texas, connecting at Tap 138kV 60008 TRIBUTE4A - 6442 REDCREEK4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/22/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0853
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Tom Green County
- Interconnecting entity
- Lightsource Renewable Energy Development LLC
- Projected COD
- 12/22/2029
- Entered queue
- 01/20/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/20/2026Entered the queue with 201 MW, projected COD 12/22/2029
- 01/20/2026Screening → FIS Requested
Other projects at this substation
| Tango Lily Solar | Solar | 201 MW | FIS Requested |