ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0688 · BESS · Travis County

Giga Texas Data Center

COD date passed

Giga Texas Data Center is a 133 MW battery storage project in Travis County, Texas, connecting at HORNSBY Substation POIB# 7047. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2025. Its projected COD of 12/15/2025 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0688
Capacity
133 MW
Fuel
BESS (BA)
Interconnecting entity
Giga Texas Energy, LLC
Projected COD
12/15/2025
Entered queue
07/30/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/30/2025
    FIS Approved → IA Signed
  • 03/17/2025
    FIS Requested → FIS Approved
  • 07/30/2024
    Entered the queue with 133 MW, projected COD 12/15/2025
  • 07/30/2024
    Screening → FIS Requested