25INR0661 · BESS · Erath County
McCrae Energy Storage
McCrae Energy Storage is a 306 MW battery storage project in Erath County, Texas, connecting at Tap 345 kV 1900 COMCHPKW_5 - 1440 COMCHESS1_5. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/25/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0661
- Capacity
- 306 MW
- Fuel
- BESS (BA)
- County
- Erath County
- Interconnecting entity
- McCrae Energy Storage, LLC
- Projected COD
- 09/25/2028
- Entered queue
- 05/01/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/17/2026FIS Requested → FIS Approved
- 12/30/2025FIS Approved → IA Signed
- 05/01/2024Entered the queue with 306 MW, projected COD 09/25/2028
- 05/01/2024Screening → FIS Requested