ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0656 · BESS · Wise County

Gilleys Energy Storage

Gilleys Energy Storage is a 306 MW battery storage project in Wise County, Texas, connecting at Tap 345 kV 1730 West Krum - 6111 Riley CKT 2. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/21/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0656
Capacity
306 MW
Fuel
BESS (BA)
Interconnecting entity
Gilleys Energy Storage, LLC
Projected COD
04/21/2028
Entered queue
05/06/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/05/2026
    FIS Requested → FIS Approved
  • 05/06/2024
    Entered the queue with 306 MW, projected COD 04/21/2028
  • 05/06/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.