25INR0583 · Wind · Archer County
Shannon Wind Repower
Shannon Wind Repower is a 18 MW wind project in Archer County, Texas, connecting at 1458 Cobb Switching Station 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0583
- Capacity
- 18 MW
- Fuel
- Wind (WT)
- Substation
- 1458 Cobb Switching Station 345 kV
- County
- Archer County
- Interconnecting entity
- Shannon Wind, LLC
- Projected COD
- 09/15/2027
- Entered queue
- 01/29/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/29/2024Entered the queue with 18 MW, projected COD 09/15/2027
- 01/29/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.