25INR0482 · Solar · Palo Pinto County

Vault Solar

Vault Solar is a 108 MW solar project in Palo Pinto County, Texas, connecting at Tap #331 Rwmiller - #320 Jaybird 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0482
Capacity
108 MW
Fuel
Solar (PV)
Interconnecting entity
PPM THR Solar
Projected COD
12/31/2027
Entered queue
06/16/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/30/2026
    FIS Approved → IA Signed
  • 12/02/2024
    FIS Requested → FIS Approved
  • 06/16/2023
    Entered the queue with 108 MW, projected COD 12/31/2027
  • 06/16/2023
    Screening → FIS Requested