25INR0432 · BESS · Anderson County
Brotherton Storage
Brotherton Storage is a 176 MW battery storage project in Anderson County, Texas, connecting at 6937 Tucker Sub 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0432
- Capacity
- 176 MW
- Fuel
- BESS (BA)
- Substation
- 6937 Tucker Sub 138kV
- County
- Anderson County
- Interconnecting entity
- BT Brotherton Storage, LLC
- Projected COD
- 05/01/2027
- Entered queue
- 04/12/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/06/2024FIS Requested → IA Signed
- 04/12/2023Entered the queue with 176 MW, projected COD 05/01/2027
- 04/12/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.