LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0401 · Wind · King County

WOE Gyp King Wind

WOE Gyp King Wind is a 304 MW wind project in King County, Texas, connecting at Tap 138kV 33798 GYP_18 – 6088 BENJ4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/31/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0401
Capacity
304 MW
Fuel
Wind (WT)
Interconnecting entity
KSK Wind Farm 1, LLC
Projected COD
08/31/2030
Entered queue
04/17/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/17/2023
    Entered the queue with 304 MW, projected COD 08/31/2030
  • 04/17/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.