25INR0370 · BESS · Rains County

Willis Storage

Willis Storage is a 176 MW battery storage project in Rains County, Texas, connecting at tap 138kV Emory North 3171 to Liberty POD 1723. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0370
Capacity
176 MW
Fuel
BESS (BA)
Interconnecting entity
Majewski Storage LLC
Projected COD
05/31/2028
Entered queue
03/13/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/07/2025
    FIS Approved → IA Signed
  • 11/08/2024
    FIS Requested → FIS Approved
  • 03/13/2023
    Entered the queue with 176 MW, projected COD 05/31/2028
  • 03/13/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.