25INR0313 · BESS · Lubbock County

Staked Plains BESS

Withdrawn

Staked Plains BESS is a 255 MW battery storage project in Lubbock County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0313
Capacity
255 MW
Fuel
BESS
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
09/18/2025
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/18/2025
    Listed as inactive

Other projects at this substation

No other projects at this substation.