25INR0288 · BESS · Robertson County

Buffalo Prairie Storage

Buffalo Prairie Storage is a 308 MW battery storage project in Robertson County, Texas, connecting at Tap 345kV 975 Jack Creek - 3400 Twin Oak. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0288
Capacity
308 MW
Fuel
BESS (BA)
Interconnecting entity
Buffalo Meadow Energy Center, LLC
Projected COD
09/30/2028
Entered queue
12/02/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/02/2022
    Entered the queue with 308 MW, projected COD 09/30/2028
  • 12/02/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.