LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0287 · BESS · Scurry County

Hide Town Energy Storage

Hide Town Energy Storage is a 103 MW battery storage project in Scurry County, Texas, connecting at 18555 Union Switch 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/11/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0287
Capacity
103 MW
Fuel
BESS (BA)
Interconnecting entity
Hide Town Energy Storage LLC
Projected COD
10/11/2029
Entered queue
01/17/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/28/2024
    Screening → FIS Requested
  • 01/17/2023
    Entered the queue with 103 MW, projected COD 10/11/2029

Other projects at this substation

No other projects at this substation.