LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0190 · BESS · Montague County

Fortissimo BESS

Fortissimo BESS is a 203 MW battery storage project in Montague County, Texas, connecting at 741 Dyemound 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/24/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0190
Capacity
203 MW
Fuel
BESS (BA)
Interconnecting entity
Fortissimo BESS, LCC
Projected COD
04/24/2028
Entered queue
10/18/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/12/2024
    FIS Requested → FIS Approved
  • 02/09/2023
    Screening → FIS Requested
  • 10/18/2022
    Entered the queue with 203 MW, projected COD 04/24/2028

Other projects at this substation

No other projects at this substation.