25INR0178 · Wind · Cottle County
Triangle Ranch Bravo
Triangle Ranch Bravo is a 200 MW wind project in Cottle County, Texas, connecting at Edith Clark 345 kV (#60500). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0178
- Capacity
- 200 MW
- Fuel
- Wind (WT)
- Substation
- Edith Clark 345 kV (#60500)
- County
- Cottle County
- Interconnecting entity
- Triangle Ranch Wind
- Projected COD
- 07/01/2028
- Entered queue
- 09/15/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/15/2022Entered the queue with 200 MW, projected COD 07/01/2028
- 09/15/2022Screening → FIS Requested
Other projects at this substation