25INR0175 · BESS · Concho County
Concho Pearl Storage
Concho Pearl Storage is a 162 MW battery storage project in Concho County, Texas, connecting at Tap 345kV 76009 Twin Buttes - 7077 Amos Creek. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/09/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0175
- Capacity
- 162 MW
- Fuel
- BESS (BA)
- County
- Concho County
- Interconnecting entity
- Concho Pearl Solar, LLC
- Projected COD
- 01/09/2028
- Entered queue
- 12/07/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/22/2024FIS Requested → IA Signed
- 12/07/2022Entered the queue with 162 MW, projected COD 01/09/2028
- 12/07/2022Screening → FIS Requested
Other projects at this substation
| Concho Pearl Solar | Solar | 172 MW | IA Signed |