25INR0164 · Solar · Lamar County
Star Dairy Solar
Star Dairy Solar is a 116 MW solar project in Lamar County, Texas, connecting at Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/12/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0164
- Capacity
- 116 MW
- Fuel
- Solar (PV)
- County
- Lamar County
- Interconnecting entity
- Star Dairy Solar LLC
- Projected COD
- 07/12/2027
- Entered queue
- 11/09/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/16/2026FIS Requested → FIS Approved
- 12/09/2024FIS Approved → IA Signed
- 11/09/2022Entered the queue with 116 MW, projected COD 07/12/2027
- 11/09/2022Screening → FIS Requested
Other projects at this substation
| Star Dairy Storage | BESS | 205 MW | IA Signed |