ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0130 · BESS · Caldwell County

Demeter Storage

Demeter Storage is a 65 MW battery storage project in Caldwell County, Texas, connecting at Tap 138kV 7224 LULING - 7216 LOCKHART. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0130
Capacity
65 MW
Fuel
BESS (BA)
Interconnecting entity
Demeter Solar, LLC
Projected COD
06/01/2029
Entered queue
08/05/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/10/2023
    Screening → FIS Requested
  • 08/05/2022
    Entered the queue with 65 MW, projected COD 06/01/2029

Other projects at this substation

Demeter SolarSolar88 MWFIS Requested
Demeter Storage 2BESS138 MWFIS Requested