25INR0078 · BESS · Goliad County
Peregrine BESS 2
Withdrawn
Peregrine BESS 2 is a 150 MW battery storage project in Goliad County, Texas, connecting at 8673 RAPTOR7A 345kV. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0078
- Capacity
- 150 MW
- Fuel
- BESS (BA)
- Substation
- 8673 RAPTOR7A 345kV
- County
- Goliad County
- Interconnecting entity
- CED Development Inc.
- Projected COD
- 07/01/2027
- Entered queue
- 08/02/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/14/2026Listed as cancelled
- 08/02/2022Entered the queue with 150 MW, projected COD 07/01/2027
- 08/02/2022Screening → FIS Requested