25INR0057 · Solar · Schleicher County
Sombrero Solar
Withdrawn
Sombrero Solar is a 352 MW solar project in Schleicher County, Texas, connecting at Tap 345kV 76003 Big Hill - 60708 Orsted. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0057
- Capacity
- 352 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 76003 Big Hill - 60708 Orsted
- County
- Schleicher County
- Interconnecting entity
- Aurora Solar LLC
- Projected COD
- 05/31/2028
- Entered queue
- 03/30/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/17/2026Listed as cancelled
- 01/03/2023Screening → FIS Requested
- 03/30/2022Entered the queue with 352 MW, projected COD 05/31/2028
Other projects at this substation
No other projects at this substation.