25INR0045 · BESS · Grimes County

Smith Lake Storage DC

Smith Lake Storage DC is a 65 MW battery storage project in Grimes County, Texas, connecting at Tap 345kV 44645 Singleton - 44900 Zenith Ckt #99. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/28/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0045
Capacity
65 MW
Fuel
BESS (BA)
Interconnecting entity
Smith Lake Solar
Projected COD
12/28/2028
Entered queue
03/07/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/30/2025
    FIS Requested → IA Signed
  • 11/02/2022
    Screening → FIS Requested
  • 03/07/2022
    Entered the queue with 65 MW, projected COD 12/28/2028

Other projects at this substation

No other projects at this substation.