LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0005 · Other · Ellis County

Tokyo TxHSR TPSS EW-1

Tokyo TxHSR TPSS EW-1 is a 50 MW other project in Ellis County, Texas, connecting at tap 138kV 2241 Ennis W - 2321 Waxahachie. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0005
Capacity
50 MW
Fuel
Other (OT)
Interconnecting entity
Texas Central Rail Holdings, LLC
Projected COD
07/15/2028
Entered queue
01/30/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/09/2019
    Screening → FIS Requested
  • 01/30/2019
    Entered the queue with 50 MW, projected COD 07/15/2028

Other projects at this substation

No other projects at this substation.