ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0572 · BESS · Cameron County

Megacharge BESS

Megacharge BESS is a 110 MW battery storage project in Cameron County, Texas, connecting at 8320 WEST HARLINGEN 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0572
Capacity
110 MW
Fuel
BESS (BA)
Interconnecting entity
SMT Harlingen III LLC
Projected COD
07/01/2028
Entered queue
06/26/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/26/2023
    Entered the queue with 110 MW, projected COD 07/01/2028
  • 06/26/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.