24INR0532 · Solar · Freestone County
Timber Cove Solar SLF
Timber Cove Solar SLF is a 100 MW solar project in Freestone County, Texas, connecting at Tap 138 kV 212 Winkler - 3510 Pin Oak. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0532
- Capacity
- 100 MW
- Fuel
- Solar (PV)
- Substation
- Tap 138 kV 212 Winkler - 3510 Pin Oak
- County
- Freestone County
- Interconnecting entity
- Freestone Solar, LLC
- Projected COD
- 06/01/2027
- Entered queue
- 05/17/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/17/2023Entered the queue with 100 MW, projected COD 06/01/2027
- 05/17/2023Screening → FIS Requested
Other projects at this substation
| Timber Cove Storage SLF | BESS | 0 MW | FIS Requested |