24INR0461 · BESS · Waller County
Augie BESS
Augie BESS is a 201 MW battery storage project in Waller County, Texas, connecting at 46560 Waller 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/17/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0461
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 46560 Waller 138kV
- County
- Waller County
- Interconnecting entity
- BRP Blue Topaz 5, LLC
- Projected COD
- 12/17/2027
- Entered queue
- 01/18/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/24/2024FIS Requested → FIS Approved
- 01/18/2023Entered the queue with 201 MW, projected COD 12/17/2027
- 01/18/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.