24INR0442 · BESS · Crockett County
Midnight Sun Energy Storage
Midnight Sun Energy Storage is a 524 MW battery storage project in Crockett County, Texas, connecting at 6601 Rio Pecos 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/29/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0442
- Capacity
- 524 MW
- Fuel
- BESS (BA)
- Substation
- 6601 Rio Pecos 138kV
- County
- Crockett County
- Interconnecting entity
- Midnight Sun Energy Storage, LLC
- Projected COD
- 06/29/2028
- Entered queue
- 11/18/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/14/2025FIS Requested → IA Signed
- 11/18/2022Entered the queue with 524 MW, projected COD 06/29/2028
- 11/18/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.