24INR0386 · BESS · Menard County
Black & Gold Energy Storage
Black & Gold Energy Storage is a 204 MW battery storage project in Menard County, Texas, connecting at 6364 Yellow Jacket Sub 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0386
- Capacity
- 204 MW
- Fuel
- BESS (BA)
- Substation
- 6364 Yellow Jacket Sub 138kV
- County
- Menard County
- Interconnecting entity
- Black & Gold Energy Storage, LLC
- Projected COD
- 07/30/2027
- Entered queue
- 07/18/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/14/2024FIS Requested → IA Signed
- 08/30/2022Screening → FIS Requested
- 07/18/2022Entered the queue with 204 MW, projected COD 07/30/2027