LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0372 · Solar · Travis County

GIGA AUSTIN SOLAR

GIGA AUSTIN SOLAR is a -53 MW solar project in Travis County, Texas, connecting at 7047 HORNSBY Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/14/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0372
Capacity
-53 MW
Fuel
Solar (PV)
Interconnecting entity
GIGA TEXAS ENERGY LLC
Projected COD
03/14/2027
Entered queue
07/18/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/26/2022
    Screening → FIS Requested
  • 07/18/2022
    Entered the queue with -53 MW, projected COD 03/14/2027

Other projects at this substation

No other projects at this substation.