24INR0372 · Solar · Travis County
GIGA AUSTIN SOLAR
GIGA AUSTIN SOLAR is a -53 MW solar project in Travis County, Texas, connecting at 7047 HORNSBY Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/14/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0372
- Capacity
- -53 MW
- Fuel
- Solar (PV)
- Substation
- 7047 HORNSBY Substation 138kV
- County
- Travis County
- Interconnecting entity
- GIGA TEXAS ENERGY LLC
- Projected COD
- 03/14/2027
- Entered queue
- 07/18/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/26/2022Screening → FIS Requested
- 07/18/2022Entered the queue with -53 MW, projected COD 03/14/2027