ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0319 · BESS · Cameron County

Burro Loco Energy Storage

Burro Loco Energy Storage is a 25 MW battery storage project in Cameron County, Texas, connecting at 8626 Resaca 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0319
Capacity
25 MW
Fuel
BESS (BA)
Interconnecting entity
VESI
Projected COD
09/15/2028
Entered queue
07/08/2022
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/08/2022
    Entered the queue with 25 MW, projected COD 09/15/2028
  • 07/08/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.