24INR0306 · BESS · Cameron County
Arroyo Storage
Arroyo Storage is a 184 MW battery storage project in Cameron County, Texas, connecting at Tap 345kV 8318 Rio Hondo - 8317 La Palma (New Gulch Substation ). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/23/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0306
- Capacity
- 184 MW
- Fuel
- BESS (BA)
- County
- Cameron County
- Interconnecting entity
- BT Cantwell Solar, LLC
- Projected COD
- 10/23/2026
- Entered queue
- 04/26/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/25/2026Energization Approved → Sync Approved
- 12/08/2025IA Signed → Energization Approved
- 04/30/2024FIS Requested → FIS Approved
- 08/10/2022FIS Approved → IA Signed
- 04/26/2022Entered the queue with 184 MW, projected COD 10/23/2026
- 04/26/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.