LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0281 · BESS · Galveston County

Red Egret BESS

Red Egret BESS is a 311 MW battery storage project in Galveston County, Texas, connecting at 38820 FREEWAY PARK 138KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0281
Capacity
311 MW
Fuel
BESS (BA)
Interconnecting entity
Red Egret LLC
Projected COD
11/17/2027
Entered queue
03/14/2022
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/21/2025
    FIS Requested → FIS Approved
  • 06/07/2023
    FIS Approved → IA Signed
  • 10/13/2022
    Screening → FIS Requested
  • 03/14/2022
    Entered the queue with 311 MW, projected COD 11/17/2027

Other projects at this substation

No other projects at this substation.