24INR0118 · Solar · Jack County
Possum Kingdom Solar
COD delayed 1×
Possum Kingdom Solar is a 262 MW solar project in Jack County, Texas, connecting at Tap 345kV 1421 Willow Creek Switch – 11523 Thomas Price. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/21/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0118
- Capacity
- 262 MW
- Fuel
- Solar (PV)
- County
- Jack County
- Interconnecting entity
- PK Solar, LLC
- Projected COD
- 06/21/2028
- Entered queue
- 09/13/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/29/2027 → 06/21/2028 (+8 months)
- 07/25/2025FIS Requested → IA Signed
- 05/23/2022Screening → FIS Requested
- 09/13/2021Entered the queue with 262 MW, projected COD 10/29/2027