24INR0117 · Solar · Freestone County
Utley Solar
Utley Solar is a 222 MW solar project in Freestone County, Texas, connecting at Tap 345kV 3381 Big Brown Switch - 3391 Jewett. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/11/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0117
- Capacity
- 222 MW
- Fuel
- Solar (PV)
- County
- Freestone County
- Interconnecting entity
- Palmera Solar Development, LLC
- Projected COD
- 05/11/2028
- Entered queue
- 09/07/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/18/2025FIS Requested → IA Signed
- 03/09/2022Screening → FIS Requested
- 09/07/2021Entered the queue with 222 MW, projected COD 05/11/2028
Other projects at this substation
No other projects at this substation.