24INR0104 · Solar · Mclennan County
Braswell Solar
Braswell Solar is a 43 MW solar project in Mclennan County, Texas, connecting at Tap 69kV 147 Lorena - 3580 Eddy Substation (Will be converted to 138kV line before 3/14/25 per TSP). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0104
- Capacity
- 43 MW
- Fuel
- Solar (PV)
- Substation
- Tap 69kV 147 Lorena - 3580 Eddy Substation (Will be converted to 138kV line before 3/14/25 per TSP)
- County
- Mclennan County
- Interconnecting entity
- Gransolar Texas Nine, LLC
- Projected COD
- 03/15/2028
- Entered queue
- 08/30/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/08/2022Screening → FIS Requested
- 08/30/2021Entered the queue with 43 MW, projected COD 03/15/2028