24INR0065 · Solar · Goliad County
Keys Hollow Solar Phase II SLF
Keys Hollow Solar Phase II SLF is a 201 MW solar project in Goliad County, Texas, connecting at 345kV Tap 8164 Coleto Creek - 8673 RAPTOR7A. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/10/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0065
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Goliad County
- Interconnecting entity
- Keys Hollow Solar, LLC
- Projected COD
- 03/10/2028
- Entered queue
- 06/17/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/02/2026FIS Requested → FIS Approved
- 10/29/2024FIS Approved → IA Signed
- 07/29/2021Screening → FIS Requested
- 06/17/2021Entered the queue with 201 MW, projected COD 03/10/2028