24INR0007 · Solar · Guadalupe County
Nockenut Springs Solar 2
Nockenut Springs Solar 2 is a 203 MW solar project in Guadalupe County, Texas, connecting at tap 345kV 5133 Elm Creek - 5915 STP ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/05/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0007
- Capacity
- 203 MW
- Fuel
- Solar (PV)
- County
- Guadalupe County
- Interconnecting entity
- Pecan Springs Energy, LLC
- Projected COD
- 06/05/2029
- Entered queue
- 09/11/2020
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/17/2023FIS Requested → IA Signed
- 09/11/2020Entered the queue with 203 MW, projected COD 06/05/2029
- 09/11/2020Screening → FIS Requested
Other projects at this substation
| Nockenut Springs Solar 1 | Solar | 203 MW | IA Signed |