23INR0494 · BESS · Hopkins County
Cartwheel BESS 1
Cartwheel BESS 1 is a 154 MW battery storage project in Hopkins County, Texas, connecting at Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0494
- Capacity
- 154 MW
- Fuel
- BESS (BA)
- County
- Hopkins County
- Interconnecting entity
- Cartwheel BESS, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 05/10/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/10/2025Energization Approved → Sync Approved
- 06/26/2025IA Signed → Energization Approved
- 04/12/2024FIS Requested → FIS Approved
- 11/10/2023FIS Approved → IA Signed
- 05/10/2022Entered the queue with 154 MW, projected COD 12/31/2026
- 05/10/2022Screening → FIS Requested