ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0486 · Gas · Lamar County

Lamar Unit 1 Repower

Lamar Unit 1 Repower is a 66 MW natural gas project in Lamar County, Texas, connecting at 1692 Paris Switch Station 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0486
Capacity
66 MW
Fuel
Gas (CC)
Interconnecting entity
La Frontera Holdings, LLC
Projected COD
12/18/2027
Entered queue
06/02/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/15/2023
    Screening → FIS Requested
  • 06/02/2022
    Entered the queue with 66 MW, projected COD 12/18/2027