23INR0464 · BESS · Henderson County
Sloan Storage
COD date passed
Sloan Storage is a 201 MW battery storage project in Henderson County, Texas, connecting at 3179 Pauline 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/27/2026. Its projected COD of 03/27/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0464
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 3179 Pauline 138kV
- County
- Henderson County
- Interconnecting entity
- Sloan Energy Storage LLC
- Projected COD
- 03/27/2026
- Entered queue
- 02/21/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/29/2022Screening → FIS Requested
- 02/21/2022Entered the queue with 201 MW, projected COD 03/27/2026
Other projects at this substation
No other projects at this substation.