23INR0425 · BESS · Chambers County
Coneflower Storage Project
Coneflower Storage Project is a 171 MW battery storage project in Chambers County, Texas, connecting at 40855 JORDON 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0425
- Capacity
- 171 MW
- Fuel
- BESS (BA)
- Substation
- 40855 JORDON 138 kV
- County
- Chambers County
- Interconnecting entity
- Coneflower Storage Project LLC
- Projected COD
- 02/28/2028
- Entered queue
- 12/20/2021
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/19/2026FIS Requested → FIS Approved
- 03/25/2024FIS Approved → IA Signed
- 07/06/2022Screening → FIS Requested
- 12/20/2021Entered the queue with 171 MW, projected COD 02/28/2028
Other projects at this substation