23INR0361 · BESS · Jackson County

Third Coast BESS

Third Coast BESS is a 103 MW battery storage project in Jackson County, Texas, connecting at 8125 Lolita substation 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0361
Capacity
103 MW
Fuel
BESS (BA)
Interconnecting entity
Third Coast BESS LLC
Projected COD
12/15/2028
Entered queue
08/24/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/02/2024
    FIS Requested → FIS Approved
  • 05/17/2023
    FIS Approved → IA Signed
  • 09/01/2021
    Screening → FIS Requested
  • 08/24/2021
    Entered the queue with 103 MW, projected COD 12/15/2028

Other projects at this substation