23INR0349 · Solar · Mclennan County
Tokio Solar
Tokio Solar is a 170 MW solar project in Mclennan County, Texas, connecting at Tap 138kV 3592 Waco Atco - 170 Cotton Belt. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/25/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0349
- Capacity
- 170 MW
- Fuel
- Solar (PV)
- County
- Mclennan County
- Interconnecting entity
- Gransolar Texas Eight, LLC
- Projected COD
- 08/25/2027
- Entered queue
- 08/12/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/06/2023FIS Requested → IA Signed
- 04/14/2022Screening → FIS Requested
- 08/12/2021Entered the queue with 170 MW, projected COD 08/25/2027