23INR0334 · BESS · Jack County
Liberty Senate Energy Storage 1
Liberty Senate Energy Storage 1 is a 207 MW battery storage project in Jack County, Texas, connecting at 1445 Burwick 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/27/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0334
- Capacity
- 207 MW
- Fuel
- BESS (BA)
- Substation
- 1445 Burwick 345kV
- County
- Jack County
- Interconnecting entity
- Senate Solar LLC
- Projected COD
- 10/27/2027
- Entered queue
- 10/03/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/03/2021Entered the queue with 207 MW, projected COD 10/27/2027
- 10/03/2021Screening → FIS Requested