23INR0310 · BESS · Lubbock County

Dunkel BESS

Dunkel BESS is a 226 MW battery storage project in Lubbock County, Texas, connecting at 59156 Yellow House Canyon 115kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/02/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0310
Capacity
226 MW
Fuel
BESS (BA)
Interconnecting entity
Momentum Energy Storage Partners
Projected COD
11/02/2027
Entered queue
06/20/2022
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/20/2022
    Entered the queue with 226 MW, projected COD 11/02/2027
  • 06/20/2022
    Screening → FIS Requested